Stone board is a new type of multi-functional building material. It currently occupies a place in the fields of overall home decoration and overall work decoration. It can be freely cut into various specifications to meet the needs of personalized space design.
Today Zhongtaojun will share with you the construction technology and process of slate wall application.
1
Slab handling
After the rock slabs are packed and installed with wooden pallets in the warehouse, they are transported to the installation destination by freight trucks arranged by the installation team.
When the installation site is located on a high-rise building, a crane needs to be used to transport the bound slate wooden pallets at high altitude. Good quality wooden pallets can support the weight of heavy rock slabs and ensure safety during transportation.
After arriving at the corresponding floor safely, the installation personnel will carry it to the specific location and wait for construction and installation.
2
Stone slab installation and construction methods
For walls below 2.4m, it is suitable to use metal corner screws + glue. For rock slabs with larger height and thickness, dry hanging is recommended for safety reasons.
①Construction method of rock slab paving
Currently, the most commonly used method in the construction of rock slabs is the gluing process. The use of specialized equipment and tools can effectively solve the problems of difficult transportation of rock slabs and unstable installation.
1. Grassroots processing
2. Spring line grids
3. Prepare rock slab glue
4. Apply slate glue
5. Moving and paving
6. Pave and compress
7. Leveling treatment
8. Empty drum inspection
9. Cleaning and caulking
②Dry hanging construction method of rock slabs
1. Dry hanging aluminum honeycomb composite rock board
▲ Dry hanging cross section of rock slab
▲Dry hanging vertical section of rock slab
2. Gluing method + stainless steel corner piece fixation
In the same way as the ground installation method, stainless steel corner pieces can be added to make the installation safer. The distance between the two corner pieces should not exceed 600mm.
▲Drilling
▲Fixed stainless steel corner piece p>
3
Protection and Acceptance
After the construction is completed, the rock slab construction party is responsible for completing protective measures such as surfaces, corners, and edges. The customer will conduct acceptance based on the drawings and the actual completed surfaces on site.
After the on-site acceptance is passed, the rock slab construction team will immediately withdraw from the site and complete the project.
▲Display of protective measures
Image and text source: Ceramic Man on the Road